High-low cost estimation method uses how many activity data points
High-low cost estimation method uses how many activity data points?
A. All historical data
B. Highest & lowest activity volume only (2 points)
C. Average of top 3 & bottom3
D. Engineering technical calculation
Answer: B
Rationale: High-low picks maximum and minimum activity level to split mixed cost into fixed/variable portions.